New Exterior - West Entrance -
06/28/2009 |
|
|
The North West Entrance - the exterior is getting the finishing touches. |
|
|
|
South Entrance -
06/28/2009 |
|
|
The south entrance with the new exterior finish system. |
|
|
|
Angled View of Canopy -
06/28/2009 |
|
|
Another view of the Main Entrance. The canopy is approx. 1200 square feet - should be able to get a couple of cars under there during inclement weather! |
|
|
|
|
Its a bit dark, but this is a little example of the acid stained flooring in the foyer. The guys from Innovative Concrete Systems have been working very hard to make our floors beautiful. This next week they should be doing the diamond polish on the floors, and then it will be beautiful. |
|
|
|
Scored concrete -
05/24/2009 |
|
|
The folks from Innovative Concrete Systems have started to score the concrete in the foyer of the church. The foyer will have 36" tiles on the diagonal, painted and diamond polished to create a beautiful, smooth, shiny floor that will be easy to care for. |
|